Secretary of the Interior Ken Salazar announced the Department of the Interior’s projects under the American Recovery and Reinvestment Act of 2009 for Ohio. Across its Bureaus, the Department will invest in Ohio as part of the recovery plan signed by the President to jumpstart our economy, create or save millions of jobs, and put a down payment on addressing long-neglected challenges so our country can thrive in the 21st Century.
Funding Overview
Ohio: $22,999,000
National Park Service: $17,476,000 ![]()
- Cuyahoga Valley: $7,797,000
- HBCU Grant: $1,750,000
- Hopewell Culture: $1,543,000
- Perry's Victory and International Peace Memorial: $6,386,000
U.S. Fish and Wildlife Service: $1,747,000 ![]()
- Carterville NFWCO: $72,000
- Cedar Point NWR: $825,000
- Ohio Partners for Fish and Wildlife: $150,000
- Ottawa NWR: $700,000
U.S. Geological Survey: $3,776,000 ![]()
- Deferred Maintenance: $3,500,000
- Deferred Maintenance - Discontinued Streamgages, Cableways, Wells: $17,000
- Upgrade Streamgages: $259,000
Projects in Ohio
Beaver Farm Prairie and Wetland Restoration- Project Number: R3ER
- TAFS: 14-1610
- Bureau: U.S. Fish and Wildlife Service
- Unit: Ohio Partners for Fish and Wildlife
- State: OH
- Congressional District: 4
- Type of Project: Habitat Restoration
- Project Status: Project on track to be completed with Recovery Act funds
- Project Status Updated: 02/17/10
- Project Number: R3GF
- TAFS: 14-1610
- Bureau: U.S. Fish and Wildlife Service
- Unit: Cedar Point NWR
- State: OH
- Congressional District: 9
- Type of Project: Deferred Maintenance
- Project Status: Project on track to be completed with Recovery Act funds
- Project Status Updated: 02/17/10
- Project Number: 152150
- TAFS: (14-1041 2009 2010) Construction and Major Maintenance - Recovery Act
- Bureau: National Park Service
- Unit: Cuyahoga Valley National Park
- State: OH
- Congressional District: 99
- Type of Project: Remediation of Abandoned Mines
- Project Status: Project on track to be completed with Recovery Act funds
- Project Status Updated: 03/03/10
- Project Number: 7890
- TAFS: (14-1041 2009 2010) Construction and Major Maintenance - Recovery Act
- Bureau: National Park Service
- Unit: Hopewell Culture
- State: OH
- Congressional District: 7
- Type of Project: Construction
- Project Status: Project on track to be completed with Recovery Act funds
- Project Status Updated: 03/03/10
- Project Number: 94479
- TAFS: (14-1041 2009 2010) Construction and Major Maintenance - Recovery Act
- Bureau: National Park Service
- Unit: Cuyahoga Valley National Park
- State: OH
- Congressional District: 99
- Type of Project: Construction
- Project Status: Project on track to be completed with Recovery Act funds
- Project Status Updated: 03/03/10
- Project Number: 155484
- TAFS: (14-5541) Historic Preservation Fund
- Bureau: National Park Service
- Unit: HBCU Grant
- State: OH
- Congressional District: 07
- Type of Project: Grants to Historically Black Colleges and Universities
- Project Status: Project on track to be completed with Recovery Act funds
- Project Status Updated: 03/03/10
- Project Number: R3CB
- TAFS: 14-1613
- Bureau: U.S. Fish and Wildlife Service
- Unit: Ottawa NWR
- State: OH
- Congressional District: 9
- Type of Project: Energy Efficiency Retrofits
- Project Status: Project on track to be completed with Recovery Act funds
- Project Status Updated: 02/17/10
- Project Number: R3EQ
- TAFS: 14-1610
- Bureau: U.S. Fish and Wildlife Service
- Unit: Ohio Partners for Fish and Wildlife
- State: OH
- Congressional District: 4
- Type of Project: Habitat Restoration
- Project Status: Project on track to be completed with Recovery Act funds
- Project Status Updated: 02/17/10
- Project Number: R3UB
- TAFS: 14-1610
- Bureau: U.S. Fish and Wildlife Service
- Unit: Carterville NFWCO
- State: OH
- Congressional District: 4
- Type of Project: Habitat Restoration
- Project Status: Project on track to be completed with Recovery Act funds
- Project Status Updated: 02/17/10
- Project Number: 141069
- TAFS: (14-1035 2009 2010) Operation of the National Park System - Recovery Act
- Bureau: National Park Service
- Unit: Cuyahoga Valley National Park
- State: OH
- Congressional District: 10
- Type of Project: Deferred Maintenance
- Project Status: Project on track to be completed with Recovery Act funds
- Project Status Updated: 03/03/10
- Project Number: 22794
- TAFS: (14-1041 2009 2010) Construction and Major Maintenance - Recovery Act
- Bureau: National Park Service
- Unit: Perry's Victory and International Peace Memorial
- State: OH
- Congressional District: 9
- Type of Project: Construction
- Project Status: Project on track to be completed with Recovery Act funds
- Project Status Updated: 03/03/10
- Project Number: N/A
- Bureau: U.S. Geological Survey
- Unit: N/A
- State: OH
- Congressional District: 99
- Type of Project: Deferred Maintenance - Discontinued Streamgages, Cableways, Wells
- Project Number: 146642
- TAFS: (14-1035 2009 2010) Operation of the National Park System - Recovery Act
- Bureau: National Park Service
- Unit: Perry's Victory and International Peace Memorial
- State: OH
- Congressional District: 9
- Type of Project: Deferred Maintenance
- Project Status: Project on track to be completed with Recovery Act funds
- Project Status Updated: 03/03/10
- Project Number: 151794
- TAFS: (14-1041 2009 2010) Construction and Major Maintenance - Recovery Act
- Bureau: National Park Service
- Unit: Cuyahoga Valley National Park
- State: OH
- Congressional District: 99
- Type of Project: Construction
- Project Status: Project on track to be completed with Recovery Act funds
- Project Status Updated: 03/03/10
- Project Number: 151629
- TAFS: (14-1041 2009 2010) Construction and Major Maintenance - Recovery Act
- Bureau: National Park Service
- Unit: Cuyahoga Valley National Park
- State: OH
- Congressional District: 10
- Type of Project: Construction
- Project Status: Additional project that will be completed with Recovery Act funds
- Project Status Updated: 03/03/10
- Project Number: B2009RV0001G
- Bureau: U.S. Geological Survey
- Unit: LAKE ERIE LABORATORY
- State: OH
- Congressional District: 9
- Type of Project: Deferred Maintenance
- Project Number: R3BA
- TAFS: 14-1613
- Bureau: U.S. Fish and Wildlife Service
- Unit: Cedar Point NWR
- State: OH
- Congressional District: 9
- Type of Project: Deferred Maintenance
- Project Status: Project on track to be completed with Recovery Act funds
- Project Status Updated: 02/17/10
- Project Number: 150900
- TAFS: (14-1035 2009 2010) Operation of the National Park System - Recovery Act
- Bureau: National Park Service
- Unit: Cuyahoga Valley National Park
- State: OH
- Congressional District: 10
- Type of Project: Deferred Maintenance
- Project Status: Project on track to be completed with Recovery Act funds
- Project Status Updated: 03/03/10
- Project Number: N/A
- Bureau: U.S. Geological Survey
- Unit: N/A
- State: OH
- Congressional District: 99
- Type of Project: Upgrade Streamgages
DOI Recovery Investments by Bureau
Select a bureau below to learn more about how each is contributing to America's economic recovery.
![]() |
![]() |
![]() |
![]() |
![]() |
Home |
About the Recovery |
Plans and Reports |
Contracts and Grants |
Contact Us
Recovery.gov | DOI Home | USA.gov
Last Updated: February 02, 2012
Content contact: recovery@ios.doi.gov