Ohio


Secretary of the Interior Ken Salazar announced the Department of the Interior’s projects under the American Recovery and Reinvestment Act of 2009 for Ohio. Across its Bureaus, the Department will invest in Ohio as part of the recovery plan signed by the President to jumpstart our economy, create or save millions of jobs, and put a down payment on addressing long-neglected challenges so our country can thrive in the 21st Century.

Funding Overview

Ohio: $22,999,000

National Park Service: $17,476,000    NPS Logo

  • Cuyahoga Valley: $7,797,000
  • HBCU Grant: $1,750,000
  • Hopewell Culture: $1,543,000
  • Perry's Victory and International Peace Memorial: $6,386,000

U.S. Fish and Wildlife Service: $1,747,000    FWS Logo

U.S. Geological Survey: $3,776,000    USGS Logo

  • Deferred Maintenance: $3,500,000
  • Deferred Maintenance - Discontinued Streamgages, Cableways, Wells: $17,000
  • Upgrade Streamgages: $259,000

Projects in Ohio

Sort by:

Beaver Farm Prairie and Wetland Restoration
  • Project Number: R3ER
  • TAFS: 14-1610
  • Bureau: U.S. Fish and Wildlife Service
  • Unit: Ohio Partners for Fish and Wildlife
  • State: OH
  • Congressional District: 4
  • Type of Project: Habitat Restoration
  • Project Status: Project on track to be completed with Recovery Act funds
  • Project Status Updated: 02/17/10
Cleanout Drainage Ditch
  • Project Number: R3GF
  • TAFS: 14-1610
  • Bureau: U.S. Fish and Wildlife Service
  • Unit: Cedar Point NWR
  • State: OH
  • Congressional District: 9
  • Type of Project: Deferred Maintenance
  • Project Status: Project on track to be completed with Recovery Act funds
  • Project Status Updated: 02/17/10
Close Four Hazardous Abandoned Oil and Gas Wells and Restore Natural Landscape
  • Project Number: 152150
  • TAFS: (14-1041 2009 2010) Construction and Major Maintenance - Recovery Act
  • Bureau: National Park Service
  • Unit: Cuyahoga Valley National Park
  • State: OH
  • Congressional District: 99
  • Type of Project: Remediation of Abandoned Mines
  • Project Status: Project on track to be completed with Recovery Act funds
  • Project Status Updated: 03/03/10
Construct Museum Collection Facility
  • Project Number: 7890
  • TAFS: (14-1041 2009 2010) Construction and Major Maintenance - Recovery Act
  • Bureau: National Park Service
  • Unit: Hopewell Culture
  • State: OH
  • Congressional District: 7
  • Type of Project: Construction
  • Project Status: Project on track to be completed with Recovery Act funds
  • Project Status Updated: 03/03/10
Eliminate Failing Septic Systems in the Village of Everett
  • Project Number: 94479
  • TAFS: (14-1041 2009 2010) Construction and Major Maintenance - Recovery Act
  • Bureau: National Park Service
  • Unit: Cuyahoga Valley National Park
  • State: OH
  • Congressional District: 99
  • Type of Project: Construction
  • Project Status: Project on track to be completed with Recovery Act funds
  • Project Status Updated: 03/03/10
Emery Hall
  • Project Number: 155484
  • TAFS: (14-5541) Historic Preservation Fund
  • Bureau: National Park Service
  • Unit: HBCU Grant
  • State: OH
  • Congressional District: 07
  • Type of Project: Grants to Historically Black Colleges and Universities
  • Project Status: Project on track to be completed with Recovery Act funds
  • Project Status Updated: 03/03/10
Install Photo Voltaic Array on Visitor Center
  • Project Number: R3CB
  • TAFS: 14-1613
  • Bureau: U.S. Fish and Wildlife Service
  • Unit: Ottawa NWR
  • State: OH
  • Congressional District: 9
  • Type of Project: Energy Efficiency Retrofits
  • Project Status: Project on track to be completed with Recovery Act funds
  • Project Status Updated: 02/17/10
Invasive species removal in western Ohio Oak Savanna habitat for the listed endangered Indiana bat.
  • Project Number: R3EQ
  • TAFS: 14-1610
  • Bureau: U.S. Fish and Wildlife Service
  • Unit: Ohio Partners for Fish and Wildlife
  • State: OH
  • Congressional District: 4
  • Type of Project: Habitat Restoration
  • Project Status: Project on track to be completed with Recovery Act funds
  • Project Status Updated: 02/17/10
NFHAP: Big Darby Creek Watershed Restoration in the Ohio River Basin
  • Project Number: R3UB
  • TAFS: 14-1610
  • Bureau: U.S. Fish and Wildlife Service
  • Unit: Carterville NFWCO
  • State: OH
  • Congressional District: 4
  • Type of Project: Habitat Restoration
  • Project Status: Project on track to be completed with Recovery Act funds
  • Project Status Updated: 02/17/10
Perform Preventative Maintenance to Replace Railroad Ties (multiple projects)
  • Project Number: 141069
  • TAFS: (14-1035 2009 2010) Operation of the National Park System - Recovery Act
  • Bureau: National Park Service
  • Unit: Cuyahoga Valley National Park
  • State: OH
  • Congressional District: 10
  • Type of Project: Deferred Maintenance
  • Project Status: Project on track to be completed with Recovery Act funds
  • Project Status Updated: 03/03/10
Preserve Perry's Victory and International Peace Memorial, Phase 1
  • Project Number: 22794
  • TAFS: (14-1041 2009 2010) Construction and Major Maintenance - Recovery Act
  • Bureau: National Park Service
  • Unit: Perry's Victory and International Peace Memorial
  • State: OH
  • Congressional District: 9
  • Type of Project: Construction
  • Project Status: Project on track to be completed with Recovery Act funds
  • Project Status Updated: 03/03/10
Removal of Discontinued Streamgage 3
  • Project Number: N/A
  • Bureau: U.S. Geological Survey
  • Unit: N/A
  • State: OH
  • Congressional District: 99
  • Type of Project: Deferred Maintenance - Discontinued Streamgages, Cableways, Wells
Repair 90 Year Old Elevator for Improved Health and Safety
  • Project Number: 146642
  • TAFS: (14-1035 2009 2010) Operation of the National Park System - Recovery Act
  • Bureau: National Park Service
  • Unit: Perry's Victory and International Peace Memorial
  • State: OH
  • Congressional District: 9
  • Type of Project: Deferred Maintenance
  • Project Status: Project on track to be completed with Recovery Act funds
  • Project Status Updated: 03/03/10
Repair Historic Tinker's Creek Aqueduct Including Removing Temporary Conveyance System
  • Project Number: 151794
  • TAFS: (14-1041 2009 2010) Construction and Major Maintenance - Recovery Act
  • Bureau: National Park Service
  • Unit: Cuyahoga Valley National Park
  • State: OH
  • Congressional District: 99
  • Type of Project: Construction
  • Project Status: Project on track to be completed with Recovery Act funds
  • Project Status Updated: 03/03/10
Replace Failing Sanitary Septic Systems in Boston Mills Historic District
  • Project Number: 151629
  • TAFS: (14-1041 2009 2010) Construction and Major Maintenance - Recovery Act
  • Bureau: National Park Service
  • Unit: Cuyahoga Valley National Park
  • State: OH
  • Congressional District: 10
  • Type of Project: Construction
  • Project Status: Additional project that will be completed with Recovery Act funds
  • Project Status Updated: 03/03/10
Replace Laboratory and dispose existing laboratory
  • Project Number: B2009RV0001G
  • Bureau: U.S. Geological Survey
  • Unit: LAKE ERIE LABORATORY
  • State: OH
  • Congressional District: 9
  • Type of Project: Deferred Maintenance
South Boundary Dike Erosion Repair
  • Project Number: R3BA
  • TAFS: 14-1613
  • Bureau: U.S. Fish and Wildlife Service
  • Unit: Cedar Point NWR
  • State: OH
  • Congressional District: 9
  • Type of Project: Deferred Maintenance
  • Project Status: Project on track to be completed with Recovery Act funds
  • Project Status Updated: 02/17/10
Upgrade Nine Miles of Railroad Line for Sustainability
  • Project Number: 150900
  • TAFS: (14-1035 2009 2010) Operation of the National Park System - Recovery Act
  • Bureau: National Park Service
  • Unit: Cuyahoga Valley National Park
  • State: OH
  • Congressional District: 10
  • Type of Project: Deferred Maintenance
  • Project Status: Project on track to be completed with Recovery Act funds
  • Project Status Updated: 03/03/10
Upgrade USGS Streamgages through purchase of High Data Rate Satellite Radios and new technology
  • Project Number: N/A
  • Bureau: U.S. Geological Survey
  • Unit: N/A
  • State: OH
  • Congressional District: 99
  • Type of Project: Upgrade Streamgages


DOI Recovery Investments by Bureau

Last Updated: February 02, 2012
Content contact: recovery@ios.doi.gov